Scope of Work:
- Rehabilitation and reconstruction of a covered channel-type water reservoir.
Covered channel 390 m long and 9 m wide, with a 3.50 m water depth.
Storage capacity: 11.5 million liters. - Rehabilitation of twin water-storage cells.
Rectangular concrete-wall structure, 38 m long by 18 m wide and 4.50 m high.
Combined storage capacity of the two cells: 3 million liters. - Rehabilitation of post-tensioned tank.
Post-tensioned reinforced-concrete cylindrical structure, 25 m in diameter and 30 m high.
Storage capacity: 30 million liters of water. - Restoration of façades and reservoir enclosure in accordance with National Heritage architectural requirements.
Restoration of 550 m of façade in accordance with the architectural standards and preservation criteria applicable to National Heritage structures. - Shotcrete slope facing.
Shotcrete and passive anchors installed on the natural slope along the side of the channel.
Area: 2,720 m².
- Rehabilitation and reconstruction of a covered channel-type water reservoir.
LOCATION
El Calvario Sector, Libertador Municipality, Caracas, Capital District.
Type of work
Architecture, Structural Rehabilitation,
Hydraulic Engineering
Specifications
- Rehabilitation and reconstruction of a covered channel-type water reservoir.
- Rehabilitation of twin water-storage cells.
- Rehabilitation of post-tensioned tank.
- Restoration of façades and reservoir enclosure in accordance with National Heritage architectural requirements.
- Shotcrete slope facing.